How a Hardware Startup Can Get CE Marked in Under 6 Months

A month-by-month plan for CE marking an electronic product in six months: directive scoping, pre-compliance, formal testing, the DoC, markings and launch.

Week three of a hardware startup's CE project. The gap analysis against EN IEC 62368-1 turns up a creepage distance on the power board that is about a millimeter short for the working voltage. On a frozen design with production tooling ordered, that finding means a respin and a slipped launch. In week three, it means a layout change before the first pre-compliance scan. (An illustrative example, not a specific company.)

That timing is most of what separates a six-month CE project from a twelve-month one. The process itself is the same length for everyone. The long projects absorb late starts, wrong assumptions about which directives apply, and rework after a formal test failure. This timeline assumes a consumer or commercial electronic device. Medical devices and machinery have additional legislation and are outside its scope.

Month 1: regulatory scoping and gap analysis

CE marking is a declaration that the product meets every piece of EU legislation that applies to it, so the first job is the list. For most electronic products it starts with three directives:

A product with a radio transmitter (Wi-Fi, Bluetooth, cellular) falls under the Radio Equipment Directive (2014/53/EU) instead of the LVD and EMC Directive, because RED covers safety and EMC itself. A connected product also falls under the Cyber Resilience Act, Regulation (EU) 2024/2847. Its reporting duties have applied since 11 September 2026, and its main requirements apply from 11 December 2027, so a product launching in 2027 needs to plan for both. Our EU certification roadmap covers the full list, including batteries and ecodesign.

Next, map each directive to its harmonised standards: typically EN IEC 62368-1 for IT and AV safety (or the EN 60335 series for household appliances), and EN 55032 and EN 55035 for EMC emissions and immunity. Then run the gap analysis: review the design against creepage and clearance, EMC provisions, material flammability ratings and marking requirements, and fix what you find before tooling is ordered. If a directive or standards question comes up here, you can ask NavJun and check the clause it cites, rather than waiting on a review cycle.

Month 2: design changes and pre-compliance testing

Make the changes the gap analysis calls for. Typical fixes at this stage include wider creepage on the PCB, added EMC filtering, higher-rated wire insulation, and plastic parts confirmed to the required UL 94 flammability class (often V-0 or V-1).

Then book time at an open EMC lab for pre-compliance scans of radiated and conducted emissions. A day there costs a fraction of a formal campaign and catches most of the issues that would otherwise surface at the accredited lab, while you still have time to fix them. Our guide to EMC design choices that decide a CE marking application covers the fixes these scans usually lead to.

Month 3: design freeze and supplier documentation

After the pre-compliance fixes, freeze the design. From here on, any change to the PCB, the enclosure or a component goes through a compliance review, because it can invalidate test results.

Then collect what the technical file needs from suppliers: component datasheets, safety data sheets, RoHS declarations covering all ten restricted substances, safety certificates for critical components (fuses, transformers, connectors), and test reports for any sub-assemblies. Our guide to RoHS 3 for hardware designers explains why declarations that stop at six substances are a problem. Start assembling the file itself:

  • a product description and intended-use statement;
  • the list of directives and harmonised standards applied;
  • design drawings and schematics;
  • a risk assessment;
  • user instructions;
  • test reports, added after formal testing.

Month 4: formal testing

Send the frozen design to a testing laboratory accredited to ISO/IEC 17025 by a national accreditation body that signs the European co-operation for Accreditation multilateral agreement. Testing typically covers safety (EN IEC 62368-1 for most IT and AV products) and EMC emissions and immunity (EN 55032 and EN 55035). A product with a transmitter adds radio testing to the relevant ETSI standards. Book early and ask for the lead time when you request the quote, since lab queues set the start date.

If the lab finds non-conformities, deal with them at once. Minor issues, such as a label correction or a documentation update, can often be closed without retesting. A design change usually means partial or full retesting, which is the cost the Month 2 scans are meant to avoid.

Months 5 and 6: declaration, markings and launch

Finish the technical file with the passing test reports, the final risk assessment and current supplier declarations. Then draft the EU Declaration of Conformity (DoC). Annex IV of the LVD and the matching annexes of the other directives set its contents. They include:

  • the product model, type and batch or serial number;
  • the manufacturer's name and address;
  • a statement that it is issued under the manufacturer's sole responsibility;
  • the legislation the product conforms to and the harmonised standards applied;
  • the place and date of issue, with the signatory's name and function.

The DoC is the manufacturer's to sign on every route. Some routes involve a Notified Body, such as EU-type examination under Module B for a radio product that doesn't apply the harmonised standards in full. There, the Notified Body issues an EU-type examination certificate for its part of the assessment. It never issues the DoC. For radio equipment, Article 10(9) of RED also requires each unit to ship with a copy of the DoC or a simplified DoC giving the web address of the full text.

The product then needs its markings. They include the CE marking, your name and postal address, the model or type identification and the importer's details where there is one, plus directive-specific marks such as the crossed-out wheeled bin for WEEE.

Finally, check who your EU responsible economic operator is. Article 4 of Regulation (EU) 2019/1020 requires one established in the EU: the manufacturer, an importer, an authorised representative or a fulfillment service provider. If an EU importer takes that role, you may not need a separate authorised representative, so map your supply chain before you appoint one. If you also plan US and Canadian sales, our comparison of UL, CSA and ETL certification covers the North American side.

Three mistakes that stretch the timeline

Most delays come from three mistakes:

  • Late compliance: treating it as a post-design step, so non-compliant decisions are locked in before anyone checks them.
  • No pre-compliance: skipping the Month 2 scans to save money, then paying for a formal failure and the rework.
  • "Just a test": assuming CE marking is a lab report, when it also covers documentation, markings and obligations after launch.

Find the creepage gap in week three

The startup in the opening found its creepage shortfall while the fix was a layout change. That is the whole method: scope the legislation in Month 1, test your assumptions in Month 2, and freeze only what has already passed a scan. Do that and six months is a realistic plan for a typical electronic product, with the formal test confirming work you have already checked.